The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
New PIO officer announced for Indiana State Police Evansville District
Valentine seeks change of venue for murder trial
Indiana Gov. Braun declares state of disaster emergency for 63 Indiana counties
Newton power plant to be closed
Lawrence County Board approves public safety tax referendum
Library district in solid financial shape
U.S. 41 road project continues in Knox County
Richland County death investigation
Vantlin named Heeps of Jeeps First Responder of the Year
Vincennes University to upgrade Beckes Park
Lawrenceville sewage plant visited by U.S. EPA
Two dead after head-on collision in Crawford County
First-ever statewide digital library resource program available in Illinois
Knox County approving preliminary solar project resolution
St Francisville to contract out bridge repair work
U.S. Postal Service will be closed in observance of Juneteenth, June 19
Feutz sworn in as new Bridgeport Police Chief