The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Rochester paving company awarded Plymouth project
Peru woman arrested for stealing copper plumbing from closed hotel
Fulton County Sheriff's Office collects hundreds of pounds of Take Back drugs
New online portal brings transparency to Indiana gas prices during declared energy emergency
ACLU of Indiana finalizes $1.2 Million in settlements over abuse at Miami Correctional Facility
Royal Center man charged with child molesting
Ride the Lightning fundraiser gains three volunteers
Hundreds of thousands of dollars in wiring recovered in Pulaski County, two detained