The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
HIP work requirements pre-screening tool now available
Stellar Pathways program accepting applicants
Fulton County Sheriff's Office issues warning about rental scams
Pulaski County Redevelopment Commission reschedules meeting for August 25
Fulton County Coroner's Office identifies deceased male found near Germany Bridge public access area
Three injured after wrong way crash on US 24
Governor Braun declares new energy emergency
IDEM announces grants to improve local waste management