The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Caston among school corporations to receive grants from Applause to AG
Prep your vehicle for winter weather
Man arrested after allegedly peeping into windows at multiple Rochester residences
Man dies from injuries sustained in hunting accident in Wabash County
Expanded opportunities for incarcerated Hoosiers through 10-year Ivy Tech partnership
Woman arrested in connection with Olson Road arson
The Andersons, Inc. to acquire Harvestone Low Carbon Partners, expanding ethanol production capacity and low-carbon fuels capabilities
High-paying jobs in advanced manufacturing with Wright Industries expansion