The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Nearly 3,000 Indiana students to explore career pathways at LENS Apprenticeship Showcase
Prep your vehicle for winter weather
Expanded opportunities for incarcerated Hoosiers through 10-year Ivy Tech partnership
Legendary Vietnam gun truck to ride DC National Veterans Parade
Rockville man arrested on CSAM charge
Conservation officers remind hunters to prioritize safety during deer season
Ex-postal worker receives sentence for stealing checks in massive $34 million fraud scheme
Christmas Nights of Lights returns to Indiana State Fairgrounds for the 2026 holiday season
MMR vaccines available at Parke County Health Department
Governor Braun extends gas tax savings
Smith, Russell earn spots on Rockville Town Board
Indiana Department of Education changing how schools are graded
Polls open statewide at 6 a.m. Tuesday
Keystone and Caledonia Farmers Elevator agree to pursue merger following successful due diligence
Indiana BMV extends hours ahead of general election
INDOT reminds drivers stay alert for road crews, Project Greenlight to increase worker visibility
GROWMARK invests in Wabash Valley Resources’ Indiana ammonia fertilizer project
Indiana State Police want everyone to stay safe this Halloween