The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Shelby County Players auditioning for upcoming Agatha Christie production
New online portal brings transparency to Indiana gas prices during declared energy emergency
Reckless homicide charged in shooting death of Adalina Perez
Southwestern's Newton earns IBCA scholarship
Plan Commission approves site development plan for apartment complex
City of Shelbyville announces month-long mental health awareness initiative
Shelbyville trails join region-wide TrailMixer Festival celebrating Central Indiana connectivity
Hancock County Nine Star Park Trail receives development grant