The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Plymouth man arrested after officer clocks motorcycle at high speed on U.S. 31
Gov. Braun declares State of Disaster Emergency for 63 Indiana Counties
Indiana Gov. Braun declares state of disaster emergency for 63 Indiana counties
STATEMENT: Gov. Braun fights for Hoosier ratepayers
U.S. Senator Young: Ban Congress from trading stocks
Indiana State Fair announces third and final wave of Hoosier Lottery Free Stage Always A Hit Concerts for 2026
Longtime Argos educator, community leader Gene Cooper passed away
Plymouth man wins $50,000 playing Powerball — now he's diving with sharks