The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Prosecutor files two counts against Emanuel Reese
INDOT reminds drivers to prepare vehicles for winter weather
Gov. Braun delivers major wins for Indiana veterans on jobs, housing and affordability
Attorney General Todd Rokita leads legal campaign to end decades-long fight and restore Ten Commandments monument at the Statehouse
Plymouth City Council hears public comment on 900-acre annexation; vote set for November 23rd
Marshall County Election Board finds commissioner candidate violated election law
Marshall County Republicans to hold 3 caucuses November 18 to fill local offices
Marshall County Commissioners approve 2027 Public Defender Contracts amid ongoing attorney shortage