Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
One driver injured in SR 9 collision
Lady Indians drop home encounter with Fairfield
GWRPC officers announced for 2026
Fritchton Agronomy Center among investments for Keystone Cooperative
Crawford and Richland Counties receive state economic funding
VU announces transition for WVUT-TV
Unit #20 Board to hold special session
ISP conduct alcohol enforcement action in Wabash County
Sumner street project to begin soon
Local couple arrested by Lawrenceville Police
Flags ordered to half-staff for Captain Seth Koval
Illinois DMV text scams continue in Lawrence and surrounding counties
Enhanced fire risk warning for southeastern Illinois and southwestern Indiana
Indiana launches enforcement campaign to target distracted driving and speeding
New Second Circuit Judge named in Richland County
Lawrenceville arrests