Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
Shelby County students invited to apply for 2026 Sister City delegation to Japan
Indiana students to get free FAFSA filing help at College Goal Sunday
Select Wings Etc. locations offering free entrée on Veterans Day
City of Shelbyville receives recognition from IDEM's Clean Communities Program
Tips for Carbon Monoxide Awareness Month
FSSA statement on SNAP benefits, one week delay
Shelby County Recorder working to stifle potential title fraud