Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
4C Health expands access to convenient virtual healthcare through ChatRx partnership
Howard County receives funds for tire cleanup
World Food Championships introduces the WFC Culinary Combine at Indianapolis this fall
Indiana Natural Resources Commission seeks input on proposed wildlife rule changes
Indianapolis woman sentenced to federal prison after threatening to kill United States Representative
Monday declared Air Quality Action Day across Indiana with changing weather pattern on horizon
U.S. Attorney’s Office hosts fraud forum, announces creation of fraud task force in Southern District of Indiana