Plymouth Street Superintendent Jim Marquardt updated members of the Plymouth Redevelopment Commission on the Hoham Drive project.
He said the project is moving along good although they did have some issues with where utilities were located. They had to change the depth of the storm drain due to issues with utility locations.
Marquardt said the temporary drive into the Holiday Inn Express is in place and they are still working with traffic patterns to the bank.
Once the storm drains are in work will begin on surface work which includes curbs and concrete along with the road surface.
Marquardt said Milestone is hoping for a better outcome than September, but they aren’t willing to set a date at this point of the project. He also noted that the project is weather dependent.
Knox County drug bust
Winter storm warning issued for area
Winter storm watch in effect for area
Unit #20 Board of Education recognizes Lady Braves and heroic students
LCMH receives federal grant funding
Lawrence County Board approves bridge construction project
Two arrested after traffic stop in Knox County
Indiana State Police seeks volunteer chaplains to support trooper wellness and resilience
St. Francisville water main break
VU Health Sciences and Learning Center to officially open in February
Earthquake in southern Illinois
American Red Cross urges the public to donate blood
State committee approves IDOC mail rule
Information sought in Lawrence County man's death
U.S. Rep. Yakym’s bipartisan BARCODE Efficiency Act Advances
Thacker joins IHA Board of Directors
St Francisville City Council moves on water tower project