Plymouth Street Superintendent Jim Marquardt updated members of the Plymouth Redevelopment Commission on the Hoham Drive project.
He said the project is moving along good although they did have some issues with where utilities were located. They had to change the depth of the storm drain due to issues with utility locations.
Marquardt said the temporary drive into the Holiday Inn Express is in place and they are still working with traffic patterns to the bank.
Once the storm drains are in work will begin on surface work which includes curbs and concrete along with the road surface.
Marquardt said Milestone is hoping for a better outcome than September, but they aren’t willing to set a date at this point of the project. He also noted that the project is weather dependent.
Applications being accepted for Governor’s 2026 Century and Half Century Business Awards
Indiana BMV extending hours for primary election
$675 million impact reported from initial Regional Economic Development funding
PHMS Amazing Shake
Parke Heritage students in competition at FFA District Contest
Indiana's February unemployment rate below national average
Indiana hiring five county executive directors in training positions
Be on the lookout for farm equipment on the road
SW Parke projected to save over a million dollars closing Montezuma Elementary
Changes coming to South Vermillion School Corporation's cell phone policy
Crawfordsville man faces list of felony child sex charges
Domestic incident results in arrest in Parke County
Clinton man nabbed in burglary case
Indiana releases update to the State Nutrient Reduction Strategy
Bridge closure to impact State Road 32 over Prairie Creek in Fountain County
13 members of armed drug trafficking and dog fighting ring sentenced