Plymouth Street Superintendent Jim Marquardt updated members of the Plymouth Redevelopment Commission on the Hoham Drive project.
He said the project is moving along good although they did have some issues with where utilities were located. They had to change the depth of the storm drain due to issues with utility locations.
Marquardt said the temporary drive into the Holiday Inn Express is in place and they are still working with traffic patterns to the bank.
Once the storm drains are in work will begin on surface work which includes curbs and concrete along with the road surface.
Marquardt said Milestone is hoping for a better outcome than September, but they aren’t willing to set a date at this point of the project. He also noted that the project is weather dependent.
Indiana Gov. Braun declares state of disaster emergency for 63 Indiana counties
Gov. Braun unveils Indiana’s exhibit for the National Mall during The Great American State Fair
Indiana State Fair announces final wave of Hoosier Lottery Free Stage concerts for 2026
Nominations now open for farmers and ranchers to serve on USDA Farm Service Agency county committees
Kokomo storm clean-up continues
Cincinnati Children’s and Parkview Health finalize to enhance pediatric care for families in northern Indiana
CBP officers in Indianapolis seize counterfeit FIFA World Cup 2026 merchandise