Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County continues to repair the roads around the Speedway Solar project.
This schedule is weather dependent and may require adjustments due to weather and any unforeseen circumstances. Daily updates will be provided each morning around 6:00 a.m.
Currently, work hours will be Monday through Friday, 8:00 a.m. to approximately 6:00 p.m.
Work crews scheduled on this project through next week.
Friday, October 24
Paving Crew
Surface Patches CR600 N between CR500 E & CR600 E
Surface patches and culvert CR700 N between CR700 E & CR750 E
Surface solar entrances and culvert CR700 E between CR700 N & CR750 N
Monday, Oct 27
Paving Crew
Surface CR750 E between SR 52 & CR750N
Tuesday, Oct 28
Paving Crew
Surface CR775 E between CR625 N & CR700 N
Surface CR600 E between CR600 N & CR700 N
Wednesday, Oct 29
Paving Crew
Surface CR700 N between CR700 E & CR500 E
Milling Crew
CR500 E between SR 52 & CR600 N
Thursday, Oct 30
Paving Crew
Surface CR625 E between CR700 N &. CR850 N
Milling Crew
CR500 E between SR 52 & CR600 N
Friday, Oct 31
Paving Crew
Surface Patches CR600 N between CR500 E & CR600 E
Surface patches and culvert CR700 N between CR700 E & CR750 E
Surface solar entrances and culvert CR700 E between CR700 N & CR750 N
Sumner boil order ends,trash pickup delayed
IDNR revises waterfowl zone
Two Lawrence County men charged
2026 Miss Illinois County Fair Pageant coming in January
Unit #20 Board hears about heat and new athletic facility proposal
Indiana's state parks offer New Years Day events
Parkview hosts annual school spelling bee
GSH receives accreditation
Crawford County man charged with sex crimes
Voter registration underway in Lawrence County
DNR receives regional award for project on former mine land near Pleasantville
Unit #10 Board hosts project open house
County to assist in Sumner street improvements
BMV announces Christmas and New Year's Day holiday hours
Bridgeport boil order lifted
Gregg Park project to move forward