Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County continues to repair the roads around the Speedway Solar project.
This schedule is weather dependent and may require adjustments due to weather and any unforeseen circumstances. Daily updates will be provided each morning around 6:00 a.m.
Currently, work hours will be Monday through Friday, 8:00 a.m. to approximately 6:00 p.m.
Work crews scheduled on this project through next week.
Friday, October 24
Paving Crew
Surface Patches CR600 N between CR500 E & CR600 E
Surface patches and culvert CR700 N between CR700 E & CR750 E
Surface solar entrances and culvert CR700 E between CR700 N & CR750 N
Monday, Oct 27
Paving Crew
Surface CR750 E between SR 52 & CR750N
Tuesday, Oct 28
Paving Crew
Surface CR775 E between CR625 N & CR700 N
Surface CR600 E between CR600 N & CR700 N
Wednesday, Oct 29
Paving Crew
Surface CR700 N between CR700 E & CR500 E
Milling Crew
CR500 E between SR 52 & CR600 N
Thursday, Oct 30
Paving Crew
Surface CR625 E between CR700 N &. CR850 N
Milling Crew
CR500 E between SR 52 & CR600 N
Friday, Oct 31
Paving Crew
Surface Patches CR600 N between CR500 E & CR600 E
Surface patches and culvert CR700 N between CR700 E & CR750 E
Surface solar entrances and culvert CR700 E between CR700 N & CR750 N
Shelby County Players present murder and mystery in 'The Unexpected Guest'
Southwestern Salutatorian turning computer interest into Cybersecurity degree
Lineup of 50 new food creations featured during this year's Indiana State Fair
National award honors Shelby County Players for community impact
Southwestern Valedictorian headed to IU to study Neuroscience
Shelbyville man arrested following pursuit
Class of 2027 graduates can apply for scholarships through Blue River Community Foundation