Plymouth Street Superintendent Jim Marquardt updated members of the Plymouth Redevelopment Commission on the Hoham Drive project.
He said the project is moving along good although they did have some issues with where utilities were located. They had to change the depth of the storm drain due to issues with utility locations.
Marquardt said the temporary drive into the Holiday Inn Express is in place and they are still working with traffic patterns to the bank.
Once the storm drains are in work will begin on surface work which includes curbs and concrete along with the road surface.
Marquardt said Milestone is hoping for a better outcome than September, but they aren’t willing to set a date at this point of the project. He also noted that the project is weather dependent.
Rep. Greene recognized for Statehouse efforts by autism advocacy groups
Ray Allison named next executive director of the Indiana State Fair Commission
Another record-breaking season at Horseshoe Indianapolis
INvestABLE Indiana announces expanded eligibility criteria beginning January 1
Governor Braun announces record year for Indiana tourism
Indiana's state parks offer New Years Day events
Indiana casinos see revenue dip in November
City interested in purchasing land for second downtown parking garage