Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
INvestABLE Indiana announces expanded eligibility criteria beginning January 1
Governor Braun announces record year for Indiana tourism
Indiana advances coal ash permitting program
Indiana's state parks offer New Years Day events
DNR receives regional award for project on former mine land near Pleasantville
Cloverdale continues to chase light at the end of the tunnel with CSX
ISP shopping safety tips