Plymouth City Attorney Jeff Houin had good news for the Plymouth Redevelopment Commission. Tuesday evening Houin said the Hoham Drive project is moving forward.
The project which was started in 2023 but a subcontractor hired by NIPSCO to relocate a gas line has delayed the project by not moving the line in a timely manner. As the project bogged down last year the contractor finally relocated the gas line but instead of installing it in the correct site, the contractor was given a plan that showed where the storm sewer was going to be so they would avoid any conflicts. Instead of installing the gas line where the plans had it, they installed the gas line where the storm sewer was located.
Tuesday evening Houin said the subcontractor was able to relocate the gas line to the correct location. That will allow Milestone to move ahead with the other utility work that needs to be completed before they can widen the road and repave it.
This project was awarded in September 2022 at a cost of $2,546,956 to low bidder Milestone. The project was to begin in the spring or early summer 2023 with completion 2024. Houin said they believe the project will be completed by August 2024.
Any additional costs due to delays caused by NIPSCO and their subcontractor will be paid for by NIPSCO.
Indiana State Police partners with DEA for Drug Take Back Day
Sumner Attendance Center conducting School Lockdown Drill Tuesday
Youth deer hunters set Illinois record, Lawrence Co. numbers up
IDNR to pause chronic wasting disease public informational meetings for fall 2026
Southern Illinois Salvation Army looking for holiday bell ringers
Illinois Farm Bureau continues rural grant program
Youth killed in southwestern Indiana accident
NTSB issues final report on train derailment in Edwards County
Red Hill Unit #10 seeking funding for BGS improvements
Lawrence and Richland County burn ban rescinded
Environmental Rules Board & IDEM act to lift fuel restrictions, reduce red tape for Indiana fire departments
Low-interest loans available for businesses, residents impacted by June 2026 severe weather
Cannonball Inn in St. Francisville under new ownership
New hanger project ready to begin soon at Mid-American Air Center
Bridgeport deals with water system matters
Sumner moving forward with Route 50 waterline expansion project