The Indiana Department of Transportation contractor Morphey Construction is moving scheduled lane closures on State Road 9 near Shelbyville to December 5.
The contractor has shifted the start back one day next week, to Tuesday. This closure with detour, will run through December7, weather permitting.
The project is to cap the tile with concrete across SR 9. If Morphey does not have a successful concrete cure at the end of their 72-hour closure they will place pinned down steel plates over the SR 9 concrete and open the road. The plates will only stay in-place until they get a satisfactory cure test.
The official detour for this project is State Road 9 to I-74 to State Road 44 to U.S. 52.
Get the most recent Shelby County Post headlines delivered to your email. Go to shelbycountypost.com and click on the free daily email signup link at the top of the page.
New Smart SNAP regulations to begin January 1
Logansport house fire damages two homes and injures two firefighters Christmas Day
Ray Allison named next executive director of the Indiana State Fair Commission
INvestABLE Indiana announces expanded eligibility criteria beginning January 1
Indiana advances coal ash permitting program
Former nonprofit CEO heads to federal prison for 33 months for $2 million embezzlement scheme