The Indiana Department of Transportation contractor Morphey Construction is moving scheduled lane closures on State Road 9 near Shelbyville to December 5.
The contractor has shifted the start back one day next week, to Tuesday. This closure with detour, will run through December7, weather permitting.
The project is to cap the tile with concrete across SR 9. If Morphey does not have a successful concrete cure at the end of their 72-hour closure they will place pinned down steel plates over the SR 9 concrete and open the road. The plates will only stay in-place until they get a satisfactory cure test.
The official detour for this project is State Road 9 to I-74 to State Road 44 to U.S. 52.
Get the most recent Shelby County Post headlines delivered to your email. Go to shelbycountypost.com and click on the free daily email signup link at the top of the page.
McCrammer sentenced to 5 years for OVWI causing serious bodily injury
Senator Mishler: State budget committee approves $200 million to expand child care access in Indiana
U.S. Congressman Yakym questions HHS Secretary Kennedy on healthcare costs, rural access, and innovation
Suspicious deer harvest leads to felony firearm charges for Shawn Myers
Walkerton man arrested for OWI after running red light in Plymouth
Sheriff Hassel welcomes new Deputy Callie Prater
Marshall County Seeking Applicants for Owner-Occupied Housing Rehabilitation Grant Program
Marian University Ancilla College to honor Mark and Amanda Feldman at Changing Lives Scholarship Dinner