The Indiana Department of Transportation contractor Morphey Construction is moving scheduled lane closures on State Road 9 near Shelbyville to December 5.
The contractor has shifted the start back one day next week, to Tuesday. This closure with detour, will run through December7, weather permitting.
The project is to cap the tile with concrete across SR 9. If Morphey does not have a successful concrete cure at the end of their 72-hour closure they will place pinned down steel plates over the SR 9 concrete and open the road. The plates will only stay in-place until they get a satisfactory cure test.
The official detour for this project is State Road 9 to I-74 to State Road 44 to U.S. 52.
Get the most recent Shelby County Post headlines delivered to your email. Go to shelbycountypost.com and click on the free daily email signup link at the top of the page.
Golden Bears Basketball/Football Golf Benefit featured full field, honored memorable teams
One dead, two held for questioning from scene of Hancock County shooting
Indiana Natural Resources Commission seeks input on proposed wildlife rule changes
Indiana unemployment rate well below national average
Indianapolis woman sentenced to federal prison after threatening to kill United States Representative
City of Shelbyville's newest fire truck 'pushed' into service
SCS board approves proposal to honor former SHS Spanish teacher
Salvation Army to host "Stuff the Bus" event at Shelbyville Walmart