Progress is being made on the lead line replacement project in the city of St Francisville.
The city council was updated on the ongoing work Wednesday night by Seth Flach, construction manager with Milano and Grunloh Engineering of Effingham.
About 40 out of over 300 meters have been replaced with work being slowed this week by weather.
It will be at least 2 more months before the project is substantially complete.
After the report. the council moved to approve payment of just over $73,000 to Bryant Construction for the work already done.
The council also approved a borrowing ordinance for $750,000 through the Illinois E.P.A. Public Water Supply loan program to be used for rehabilitation work on the city water tower.
The over $11 million Cannonball Bridge project was also reported to be about 58% complete.
Moorhead was among top athletes during golden Shelbyville High School sports era
More than one-third of Christmas tree home fires occur in January
Proposed data center focus of Shelbyville Common Council and Plan Commission meetings
First 2026 City of Shelbyville meetings begin Monday
Sugar Foods with new production and distribution facility in Whiteland