The Water Street Townhouses are expected to be ready for occupancy in January.
Tuesday evening, members of the Plymouth Redevelopment Commission were given an update on the project by City Attorney Jeff Houin.
The alley between Michigan and Water Streets has been demoed in preparation for paving. Houin said additional concrete work on the north end of the development behind Dr. Joel Schumacher’s Office caused a delay. The concrete work along Water Street in front of the townhouses and on the south end along the retail space still has to be completed.

Paving contractor Phend and Brown plans to complete the alley and parking lot this month, although the project is weather-dependent. It was noted that once paving is finished, the alley will be open, but the parking lot will remain closed until construction is complete.

Houin informed commission members that the street lighting has been roughed in, and the siding crew will be on site this week to complete the front siding and awning above the doorways.
The mechanical units have been installed on the inside, and drywall is underway. For additional information, check out www.water-street-townhomes.com

Gov. Braun declares Gas Tax Holiday to save money for Hoosiers
EPA approves Indiana plan to help air quality in national parks
USDA announces the creation of the USDA National Proving Grounds Network to Strengthen U.S. Farm and Ranch Profitabilit
Boating on Barbee and Tippecanoe Lakes Chain, and Lake Wawasee is restricted
Marshall County Police Depts to increase patrols to target distracted driving and speeding
Marshall County Property Tax Bills mailing this week; May 11 due date
Two arrested on felony drug charges following suspicious vehicle report Thursday
Two Plymouth residents arrested in connection with local restaurant theft