A complete rehabilitation of Runway 5/23 at the Kokomo Municipal Airport is scheduled to begin this summer, made possible by significant funding support from the Federal Aviation Administration (FAA).
This project, originally planned to be completed in phases over several years, can now be finished entirely during the current construction season due to the FAA's commitment. The total cost of the project is $8,179,676.67.
The rehabilitation will be conducted in three phases to minimize the impact on airport operations and reduce the time both runways are closed. Runway 5/23 is scheduled to close beginning August 4 and will remain closed for the duration of the project, which is expected to last approximately 72 days.
Runway 14/32 will also experience temporary closures to accommodate work in the intersection area. It will be closed from approximately August 20 through September 4, with additional short-term closures anticipated in late September for runway grooving and in October for final painting.
Gov. Mike Braun Orders Flags Lowered to Half-Staff in Honor of Captain Seth Koval
$50K winning Powerball ticket sold in Plymouth
State Rep. Jack Jordan warns Hoosiers of rising court and toll road phishing scams
Dink, Drive, and Do Good: Plymouth Lions Club to host 2nd annual Pickleball Tournament
ISP announces increased patrols to target speeding and distracted driving
Red Cross partners with 'Life is Good' for spring blood drives in Marshall County
U.S. Senators Young, Rosen introduce bill to boost housing supply, lower costs by supporting housing small businesses
Fire damages two-story building used as a church east of Plymouth