A change order for the Gibson LaPorte Streets Community Crossing project that was recently completed was approved during Monday’s Board of Public Works and Safety meeting.
City Engineer, Dan Sellers told the board there was about 250 feet of Gibson Street, near Roy Street, that had substandard soils so the contractor had to do additional excavating of the soils. They also had to haul in additional stone to create a solid base and applied two layers of asphalt on that section or street.
The change order was for an additional $72,996.85. Because this project used the city’s Community Crossing Matching Grant funds, the additional is totally the responsibility of the city with no additional grant funds.
Wabash Valley Progressives to host annual meeting
Lawrenceville city officials to meet with EPA
Hoosiers may qualify for free well water testing
St. Francisville City Council approves street and alley work
LCMH moving to new medical records system
Freelandville Methodist Church receives grant from native of the community
Indiana Gov. Mike Braun declares gas tax holiday
School threat investigated in White County
Road closure announced for bridge project in Lawrence County
Lady Indians drop home encounter with Fairfield
Fritchton Agronomy Center among investments for Keystone Cooperative
Crawford and Richland Counties receive state economic funding
VU announces transition for WVUT-TV
Unit #20 Board to hold special session
ISP conduct alcohol enforcement action in Wabash County
Sumner street project to begin soon