Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
Indiana AG warns of human trafficking during Final Four
Truck traffic restricted for roundabout work on State Road 28 in Tipton
Bills signed to protect kids from exploitation on social media, crack down on online predators
Voter registration deadline April 6
Flags ordered to half-staff for Captain Seth Koval
National Band Expo on May 16 at Sweetwater
Indiana launches enforcement campaign to target distracted driving and speeding
Indianapolis Indians named title partner of the 2026 Indiana State Fair