Desri has contracted with Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County to repair the roads around the Speedway Solar Farm project.
Below is a schedule for Wednesday, November 5.
Currently, work hours will be Monday through Friday, 7:30 am to approximately 6:00pm. .
Daily updates will be sent every morning at approximately 6:00 am.
Stone Crew
Place shoulder stone in deep areas along CR700 N from CR500 E to CR700 E
CR700 N will be closed during stone placement. The equipment will take up most of the roadway.
Paving Crew
Complete Paving on CR500 E from end of Production yesterday to CR600 N
CR500 E will be closed to through traffic from 8:00 am to approximately 6:00 pm. Flaggers will be onsite to assist motorists.
INvestABLE Indiana announces expanded eligibility criteria beginning January 1
Governor Braun announces record year for Indiana tourism
Indiana advances coal ash permitting program
Former nonprofit CEO heads to federal prison for 33 months for $2 million embezzlement scheme
Indiana's state parks offer New Years Day events
ISP shopping safety tips
4C Health expands crisis care continuum with Subacute Stabilization Certification