Plymouth Street Superintendent Jim Marquardt updated members of the Plymouth Redevelopment Commission on the Hoham Drive project.
He said the project is moving along good although they did have some issues with where utilities were located. They had to change the depth of the storm drain due to issues with utility locations.
Marquardt said the temporary drive into the Holiday Inn Express is in place and they are still working with traffic patterns to the bank.
Once the storm drains are in work will begin on surface work which includes curbs and concrete along with the road surface.
Marquardt said Milestone is hoping for a better outcome than September, but they aren’t willing to set a date at this point of the project. He also noted that the project is weather dependent.
9 charged in Miami Correctional Facility death investigation
Chariot Automotive Group and Ivy Tech celebrate first Business graduates
Safe Zones enforcement to resume on I-70 in Hancock Co., begin on I-65 in Jasper Co.
IDHS focuses on raising awareness during Severe Weather Preparedness Week, March 8-14
Penny-rounding for retailers
Fatal head-on in Clinton County involves injured Frankfort officer
Master Trooper Shanks recognized for 15 years of service