The lead line replacement project in the city of St. Francisville is approximately half completed.
That according to a summary given to the City Council Wednesday night by project engineer Seth Flach of the firm Milano and Grunloh out of Effingham.
He indicated that 149 meters have now been replaced and the work continues.
It is anticipated that the project could wrap up in mid-June, weather permitting.
The council did approve payment to Bryant Construction for the work already done.
The over $11 million Cannonball Bridge project is about 58% complete.
Samron poured concrete on Wednesday of this week as the work progresses.
The council did approve the date of Friday, May 16th as City Wide Cleanup Day.
Additional information regarding the annual affair will be released in the coming days by the city.
Man wanted on a warrant in Fulton and other multiple counties arrested fleeing from officers
National 811 Day reminds you to call before you dig
Secretary of State's Office hosting $2 Tuesday at the Indiana State Fair
Argos farmer dies in grain bin incident on family farm
Open house to see Rochester park improvements on Tuesday
Pursuit, crash, arrests Friday