A complete rehabilitation of Runway 5/23 at the Kokomo Municipal Airport is scheduled to begin this summer, made possible by significant funding support from the Federal Aviation Administration (FAA).
This project, originally planned to be completed in phases over several years, can now be finished entirely during the current construction season due to the FAA's commitment. The total cost of the project is $8,179,676.67.
The rehabilitation will be conducted in three phases to minimize the impact on airport operations and reduce the time both runways are closed. Runway 5/23 is scheduled to close beginning August 4 and will remain closed for the duration of the project, which is expected to last approximately 72 days.
Runway 14/32 will also experience temporary closures to accommodate work in the intersection area. It will be closed from approximately August 20 through September 4, with additional short-term closures anticipated in late September for runway grooving and in October for final painting.
Rochester woman arrested after allegedly resisting arrest and battering a police officer
Two drivers injured after three vehicle crash on US 35
Student entrepreneurs take the stage at FEDCO’s 7th annual First Pitch Event
Operation Upper Hand: More than 65 arrested on over 200 criminal charges
Person identified for making threat to Lewis Cass
Cass County Pride announces new board members during annual meeting
Friday is National Wear Red Day