The Town of Culver will begin construction on the Lake Shore Drive Road Widening Project on Monday.
In March, Culver Town Manager Kevin Dante told members of the Town Council that the town had received $1,011,810.75 in Community Crossing Matching Grant Funds. The Community Crossing Funds were allocated to widen North Lake Shore Drive between the intersection of State Road 10 and State Road 17, going south to Academy Road. The project also encompasses a stormwater initiative and curbing.
The construction zone for this project is located on Lake Shore Drive between State Road 10 and Academy Road.
Two-way traffic will be closed; however, the town will attempt to maintain single-lane traffic through this area to provide access to Park and Shop, as well as First National Bank of Monterey.
Any concerns or questions can be addressed to Kevin Dante at kdanti@townofculver.org.
Shelby County Public Library renovation underway schedule changes begin next week
Former Indiana online charter schools director convicted of wire fraud and conspiracy in largest theft of public funds ever prosecuted in Southern District of Indiana
Muncie teen killed in Hancock County car-semi crash
SCPL seeks public input for strategic plan
Nearly 3,000 Indiana students to explore career pathways at LENS Apprenticeship Showcase
Housing increasing in Rushville aided by READI
Prep your vehicle for winter weather
SHS students attend Indiana Junior Classical League at Ball State University