This past week, LaPorte Construction completed all the sidewalk and bridge railing work for the Randolph Street Bridge Replacement Project. They also smoothed all the concrete for the rail and piers and completed all concrete work.
ABC Grooving was in and has grooved the bridge deck. Michiana Contracting has placed the lighting handholes and most of the cable duct.
Last week, the park department reset its bricks in the new walk.
Toward the end of this week, Michiana Contracting may be on site to continue with the lighting work. They still need to finish the cable duct, foundations, service point, and set the poles and lights.
E&B Paving is expected to pave the surface around October 7th. Once the lighting project is complete, Slussers Green Thumb will be in to complete the seeding, and once the pavement is done, then striping can be done.
LaPorte Construction will not be on site this week because any remaining work cannot be completed until the subcontract work is finished.
LaPorte Construction estimates they are 86% complete with the project.
SHS students attend Indiana Junior Classical League at Ball State University
Expanded opportunities for incarcerated Hoosiers through 10-year Ivy Tech partnership
Veterans Day free admission to Indiana DNR properties
Conservation officers remind hunters to prioritize safety during deer season
54th Annual Gift and Hobby Show in Shelbyville Saturday
Ex-postal worker receives sentence for stealing checks in massive $34 million fraud scheme
Christmas Nights of Lights returns to Indiana State Fairgrounds for the 2026 holiday season
DCMH introduces new app to support families through pregnancy, early parenthood