The Red Hill Unit #10 Board of Education has voted to proceed forward with two district school projects.
One will be to replace the condensate pump at Bridgeport Grade School for $4,425
The other would be to sand and repaint the north junior high gym at the Jr/Sr high school for approximately $31,000.
That work would be completed in the summer.
Superintendent Jakie Walker told GIANT-FM News that a special session of the board is planned in the future.
It would be to discuss and take possible action on the major projects being considered through collaberation with the Chicago-area engineering firm ENGIE.
The board also moved to continue co-op agreements with Lawrence Unit #20 in the sports of wrestling and cross country.
Waldron Healthcare invites community to a free, fun-filled Easter celebration on March 28
Indiana announces launch of enhanced system for Hoosier military and overseas voters
Body found in river is missing Shelbyville man
Pavement rehabilitation project to begin on State Road 252 in Edinburgh
Man killed in Hancock County car-pedestrian accident
Easter Egg Hunt Saturday at Kennedy Park
Safe Zones enforcement begins April 1 on I-74 in Decatur and Shelby counties
Board of Works approves three SCUFFY roadblock locations