Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County has been contracted to repair the roads around the Speedway Solar project.
DOCI plans to start the work on Monday. The projects consist of milling, patching, pipe replacement, widening, and resurface.
This schedule is weather dependent and may require adjustments due to weather and any unforeseen circumstances. CR500 E will utilize flaggers to control traffic. All other roads due to their width will be closed during the work.
Currently, work hours will be Monday through Friday, 8:00 am to approximately 6:00pm. These hours will be adjusted when time changes.
Speedway Solar Project Schedule
Monday, October 20
Milling crew
County Road 625 East between CR500 N & CR600 N
Sawcut Pipes
Intersection CR700 N & CR700 E
Intersection CR750 N & CR700 E
Intersection CR700 N & CR750 E
CR600 N between CR625 E & CR700 E
Tuesday, October 21
Mill Crew
CR600 N between CR600 E & CR700 E
Patching Crew
CR700 N between CR500 E & CR700 E
Pipe Crew
Intersection CR700 N & CR700 E
Wednesday, October 22
Mill Crew
CR775 E between CR625 N & CR700 N
Patching Crew
Continue Patching - CR700 N between CR500 E & CR700 E
Thursday, October 23
Mill Crew
CR750E between CR700 N & US52
Pipe Crew
Intersection CR750 N & CR700 E
Intersection CR700 N & CR750 E
CR600 N between CR625 E & CR700 E
Patching Crew
CR600 N between CR600 E & CR700 E
CR625 E between CR600 N & CR500 N - If needed
Friday, October 24
Mill Crew
Continue - CR750 E between CR700 N & US52
Patching Crew
Assorted radius widening & solar farm approaches
CR750 E between CR700 N & US52