Road crews continues improvements around Shelby County solar project

Friday, October 24, 2025 at 8:37 AM

By Staff report

Dave O’Mara Contractor, Inc. (DOCI) under the supervision of Shelby County continues to repair the roads around the Speedway Solar project.  

This schedule is weather dependent and may require adjustments due to weather and any unforeseen circumstances.  Daily updates will be provided each morning around 6:00 a.m.

Currently, work hours will be Monday through Friday, 8:00 a.m. to approximately 6:00 p.m. 

Work crews scheduled on this project through next week.

Friday, October 24

Paving Crew

Surface Patches CR600 N between CR500 E & CR600 E

Surface patches and culvert CR700 N between CR700 E & CR750 E

Surface solar entrances and culvert CR700 E between CR700 N & CR750 N 

Monday, Oct 27

Paving Crew

Surface CR750 E between SR 52 & CR750N

Tuesday, Oct 28

Paving Crew

Surface CR775 E between CR625 N & CR700 N

Surface CR600 E between CR600 N & CR700 N

Wednesday, Oct 29

Paving Crew

Surface CR700 N between CR700 E & CR500 E

Milling Crew

CR500 E between SR 52 & CR600 N

Thursday, Oct 30

Paving Crew

Surface CR625 E between CR700 N &. CR850 N

Milling Crew

CR500 E between SR 52 & CR600 N

Friday, Oct 31

Paving Crew

Surface Patches CR600 N between CR500 E & CR600 E

Surface patches and culvert CR700 N between CR700 E & CR750 E

Surface solar entrances and culvert CR700 E between CR700 N & CR750 N