The Marshall County Highway Department will be purchasing a Total Patcher after the County Council gave its support to using Cum Cat funds.
On Monday, Highway Superintendent Jason Peters said Commissioner Stan Klotz signed a contract to purchase the new equipment on July 31st, the day before a $5,000 increase went into effect. The commissioners ratified Klotz’s signature on the contract.
The county attorney presented a resolution to purchase the Total Patcher from Equipment Marketing Company without the requirement of seeking bids. He said, “The state has special purchasing statutes. There are various scenarios where you are allowed to buy equipment without going through a normal procurement process of bidding or seeking quotes. Generally, those involve some savings. One example is when the device is offered at a rate that another state agency has already secured through a broader procurement process.” The attorney said INDOT has secured the pothole patching machine through a Quantity Purchase Award Agreement. Surrisi went on to say, “This is a permitted way to buy the equipment without bids.”
The commissioners unanimously approved the procurement resolution.
The Council will appropriate the funds for the purchase at their August 11th meeting. The price is $97,500.
Red Cross calls need for blood donations urgent, Morristown blood drive Friday
Marietta Fire Station, Blue River Trail to partner with IU on new public art and design projects
Two meetings this week regarding potential data center campus in Shelbyville
Shelby County Sheriff warns of another scam in the area
Safe Zones enforcement to resume on I-70 in Hancock Co., begin on I-65 in Jasper Co.
Class 2A, No. 6 Triton Central tops Scecina for second consecutive sectional title
IDHS focuses on raising awareness during Severe Weather Preparedness Week, March 8-14