The Bi-State Authority, which governs the Mid-American Air Center located northeast of Lawrenceville met this week and were informed of the completion of a major project.
Airport assistant manager Devin Hill told the board that the ODALS construction project was completed on time on April 25th. They are now waiting on a Federal Aviation Administration (FAA) flight test and training for them to be fully operational. The flight will take about 2 hours and will cost around $7100.
Three bids were received for the hanger project with Precise Construction coming in as the low bidder at $1,296.368. They were taken under advisement for further study and review.
The airport is applying for FY2026 Community Project Funding. This money will be used to help pay for the new Sewer Mound System, eliminating the current sewer plant. The amount of funding needed is $240,000 with $48,000 in matching funds from the airport.
Shelby County Plan Commission moves up August meeting on data center ordinance with moratorium deadline approaching
$50,000 winning Powerball ticket sold in Greenfield
Countrymark fueling stations hosting Fueling Freedom on Friday
Arrive AI successful initial deployment at Hancock Health
DJM Investments nearing groundbreaking for new apartment complex in Shelbyville
May unemployment rate in state still below national average
Shelby County Plan Commission to consider data center ordinance at Tuesday meeting
SCS updates student handbooks with new cell phone and smartwatch policy