The Red Hill Junior/Senior High School (RHJSHS) south gymnasium project is continuing toward completion.
The Unit 10 Board of Education were updated on the project Thursday by superintendent Jakie Walker. He told GIANT-FM News that several floors have now been laid down with epoxy, and the concession stand area is nearly complete.
The installation of the lockers in the varsity dressing room and other areas is expected to take place next week once they arrive.
The bathrooms were also now complete.
Additional work will continue in the coming days.
Walker says the project remains on schedule for Nov. 3 completion date. An open house date will be set up for the public to see the work soon afterward.
Indiana Corn Marketing Council seeks farmers to serve on its board of directors
ICAC looks to grow in search for online predators
Annual Report available from Greencastle Fire Department
Rutenberg eyes seat on Cloverdale Town Board
Haggard looks to unseat Congressman Baird
Nominations being accepted for 2026 John Arnold Award for Rural Preservation