The Red Hill Junior/Senior High School (RHJSHS) south gymnasium project is continuing toward completion.
The Unit 10 Board of Education were updated on the project Thursday by superintendent Jakie Walker. He told GIANT-FM News that several floors have now been laid down with epoxy, and the concession stand area is nearly complete.
The installation of the lockers in the varsity dressing room and other areas is expected to take place next week once they arrive.
The bathrooms were also now complete.
Additional work will continue in the coming days.
Walker says the project remains on schedule for Nov. 3 completion date. An open house date will be set up for the public to see the work soon afterward.
Howell looks back fondly on time with Cloverdale Town Board
Tancak reflects on tenure with Cloverdale Town Board
Brandon Tancak, Brice Howell resign from Cloverdale Town Board
Indiana Department of Veterans Affairs, American Legion Department of Indiana sign landmark agreement
Brazil man arrested on rape, other charges
GE Aerospace to make millions of dollars of investment in Terre Haute, Lafayette