Duke Energy is seeking IURC approval to build a new natural gas-fired power plant in Vermillion County, including permission to recover costs through future rates.
In testimony, the utility estimates project costs at approximately $3.33 billion.
Duke Energy customers have the opportunity to comment for the formal record on the utility's proposal to build and operate a new power plant in Vermillion County. The proposed 1,476-megawatt facility would include two natural gas-fired generating units and would replace the coal-fired units at the Cayuga Generating Station.
The project could lead to a 5.4% rate increase for customers between 2026 and 2032.
The OUCC filed the following testimony on May 8 recommending denial of the request as proposed:
Duke Energy filed its petition and the following testimony on Feb. 11:
All publicly filed documents in this case (Cause No. 46193) are available on the IURC's website.
The utility is scheduled to file rebuttal testimony on May 29.
IURC public field hearings were held in Bloomington and Terre Haute in April.
Free admission to DNR properties for veterans, active-duty military, Nov. 11
Indiana Grown Holiday Box highlights local businesses for the third year
Christmas Nights of Lights returns to the Indiana State Fairgrounds
Indiana State Police wants everyone to stay safe this Halloween
Nominations being accepted for Indiana Certified Crop Adviser (CCA) of the Year
Seminary Square Project takes step forward with new developer
BMV warns customers of new scam text messages
National FFA Convention & Expo to call Indy home through 2040