The $3 million bridge replacement project on Randolph Street in Plymouth is 52% complete, according to contractors LaPorte Construction.
Last week, LaPorte Construction drove piling for bent 4. All the piles have been driven to bearing and cut and filled with concrete. Forms were placed, and Fort Wayne Reinforcement installed the rebar in bent #4, and the bent was poured on Friday. LaPorte also placed some rip-rap on the north bank, and the overhangs, decking, and deck pans on beam spans one and two.
This week, LaPorte Construction plans to finish placing all the riprap on the north and south banks as well as pouring the upper portion of bent 1. The last set of beams is scheduled for delivery and placement on July 21st. They also plan to install the end bent drains on both sides of the bridge.
New milestones and completion dates have been discussed with INDOT and the contractor. Marshall County and the City of Plymouth have both agreed on the dates, and the agreement has been sent to the contractor for review and signatures so it can be passed on to the county.
According to USI Consultants and LaPorte Construction, the project is on schedule. While the entire project isn’t expected to be complete by the Blueberry Festival, the bridge should be open to pedestrian and tram traffic.

Photos provided.
Southwestern's Newton earns IBCA scholarship
Plymouth High School boys basketball coach Greg Miller resigns after two seasons
Gov. Braun highlights skilled trades, apprenticeships, and Workforce Development in Visit to Central Midwest Carpenters
Plymouth Board imposes $6,000 in fines over stalled Red Rock Inn demolition and bond
Plymouth Police arrest four for driving violations during busy Sunday traffic stops
Plymouth Police make three OWI arrests over the weekend, including two with high BACs
Community rallies to support Plymouth Street Superintendent in need of life-saving transplant
Early Bird registration for art & food vendors: 12th Annual 'ARTS in the Street' Festival downtown Plymouth
