The Water Street Townhouses are expected to be ready for occupancy in January.
Tuesday evening, members of the Plymouth Redevelopment Commission were given an update on the project by City Attorney Jeff Houin.
The alley between Michigan and Water Streets has been demoed in preparation for paving. Houin said additional concrete work on the north end of the development behind Dr. Joel Schumacher’s Office caused a delay. The concrete work along Water Street in front of the townhouses and on the south end along the retail space still has to be completed.

Paving contractor Phend and Brown plans to complete the alley and parking lot this month, although the project is weather-dependent. It was noted that once paving is finished, the alley will be open, but the parking lot will remain closed until construction is complete.

Houin informed commission members that the street lighting has been roughed in, and the siding crew will be on site this week to complete the front siding and awning above the doorways.
The mechanical units have been installed on the inside, and drywall is underway. For additional information, check out www.water-street-townhomes.com

Marshall County Democratic Party makes statement on Commissioner's declaration of a Second Amendment Sanctuary County
Make plans to attend or participate in Plymouth's annual Lighted Christmas Parade and Tree Lighting
State Comptroller’s Office warns of misleading mailing
Plymouth Police arrest one on a warrant, one for driving without a license
Rex sentenced to 11 years in DOC for Child Molesting and Sexual Misconduct
Marshall County Police Dept. to increase holiday patrols to promote safe roads
Heartland Church with unique wedding opportunity this weekend
Toy Show coming to Fulton County Museum this weekend