The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
City of Plymouth meetings Monday at 6 & 6:30
Zachary Gipson hosts Evie Ladin on the Wild Rose Moon Radio Hour
Local insurance agent Emily Haskins announces opening of new office in Plymouth
American Revolution Experience traveling exhibit at Marshall County Museum Oct. 14-25
Marshall County Council meets Monday
U.S. Senator Young, colleagues urge FDA to continue to stand for life, reevaluate abortion drug approval
Plymouth man arrested by city police in Arby's drive thru for OWI
Unwanted guest on Thurmer Trail arrested on warrant and possession of controlled substance