The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Gov. Mike Braun orders flags to half-staff for Pearl Harbor Remembrance Day
Stay safe; always assume you are on ‘thin ice’
Niles man dies in US 31 crash near Argos; passenger injured
Plymouth man arrested on OWI following traffic stop
Bremen man arrested following single-vehicle crash, alleged DUI
Wrong-way driver causes head-on collision on U.S. 30
Jose Perez arrested for alleged speeding on Michigan Street
Plymouth man arrested following battery complaint at Economy Inn