Adam Parkhouse, Director of Stakeholder Services for INDOT out of the LaPorte District updated Mayor Robert Listenberger on the new bridge project over the railroad on U.S. 31
In an email, he said, “On Wednesday, crews will be setting beams for the new bridge. There are six individual beam settings that will take place throughout the day, each one requiring a full closure of no longer than 30 minutes as the crane lowers each beam into place. Typically, they get them in place quicker than that, especially after they get that first one out of the way, so hopefully that’s the case.”
Parkhouse gave some additional information on activities that will be happening later this week and into next week as part of the new railroad bridge project on U.S. 31.
Following the installation of the bridge beams on Wednesday, the next few days there will be some shorter-term closures of 10 to 15 minutes each while the cranes are disassembled. Between Thursday and Friday, there will be up to eight total closures while one crane is disassembled, then eight more closures on Monday and Tuesday, March 11th and 12th while the other crane is disassembled.
South Bend man arrested by city police for driving without a license
Knox man arrested at Walmart Wednesday for PI and disorderly conduct
McDonald’s of greater Indiana honors veterans with free meals on Veterans Day
Coach Bob Knight Indiana Hoosiers Championship Bobblehead Series to celebrate 50th anniversary
Indiana State Fairgrounds announces expansion of Hoosier Lottery Stage, and partnership with MOKB Presents
U.S. Senator Young's statement on War Powers Resolution
M.C. Regional Sewer District cancels upcoming meeting
Plymouth Police Dept. to purchase new tasers