The developer will pay to pave the Water Street parking lot in Plymouth this month, and the city will pay for the alley between Garro Street and Washington Street.
During the Board of Public Works and Safety meeting on October 27th, City Attorney Jeff Houin said that when the contractor hired by developer Kevin Berger paves the parking lot behind the Water Street Townhouses, the city will have that same contractor pave the alley after NIPSCO moved poles back so the alley can be used as the exit for the parking lot.
Alley excavation is scheduled for this week to ensure there are no surprises under the asphalt. The alley will then be prepped for the new pavement, which is scheduled for the week of November 13th through the 18th. Houin said when the paving is complete, the alley will be open, but the parking lot will remain closed until construction on the townhouses is completed.
The dumpsters in the alley may be temporarily placed in parking spaces on Washington or Garro Street.
Indiana Natural Resources Commission seeks input on proposed wildlife rule changes
IDOT Traveler Survey available
Unit #20 to start school with split schedule
Yochum to run for Indiana State Senate
Air Quality Alert issued for southeastern Illinois
Sumner seeking water project grant
2026 Illinois prevailing wage rates released
U.S. Attorney’s Office hosts fraud forum, announces creation of fraud task force in Southern District of Indiana
IDNR seeking office coordinator for Red Hill State Park
Lawrence County Board votes to regulate synthetic intoxicants
Lawrence Correctional officers plead guilty to inmate civil rights violations
AARP Indiana celebrates YMCA Vincennes Community Challenge grants with check presentation
Lawrence County Democrats to host candidate town hall meeting
Niemerg appointed to Illinois House investigative committee
Lawrenceville Police release June activity report
Two arrested by Lawrence County law enforcement
New Miss Lawrence County Fair Queen crowned