Progress is being made on the lead line replacement project in the city of St Francisville.
The city council was updated on the ongoing work Wednesday night by Seth Flach, construction manager with Milano and Grunloh Engineering of Effingham.
About 40 out of over 300 meters have been replaced with work being slowed this week by weather.
It will be at least 2 more months before the project is substantially complete.
After the report. the council moved to approve payment of just over $73,000 to Bryant Construction for the work already done.
The council also approved a borrowing ordinance for $750,000 through the Illinois E.P.A. Public Water Supply loan program to be used for rehabilitation work on the city water tower.
The over $11 million Cannonball Bridge project was also reported to be about 58% complete.
More than one-third of Christmas tree home fires occur in January
Miss Jackson County named Miss Indiana State Fair, Miss Howard County in Top 10
Leadership change announced for Greater Kokomo Downtown Association
4C Health updates role title to better reflect recovery-oriented care
Gov. Braun, AG Rokita ask Federal Court to lift 20-year ban on Historical Monument at Indiana Statehouse
New Smart SNAP regulations to begin January 1
Logansport house fire damages two homes and injures two firefighters Christmas Day