Donnie Davidson, the City of Plymouth Utility Superintendent updated members of the Board of Public Works and Safety on several projects during last week’s meeting.
The million-dollar solar project at the Wastewater Treatment Plan was commissioned last week and Davidson said, “We are producing electricity.” In fact, the plant has been able to produce more energy than the treatment plant needs to operate.
The test well is providing adequate water volume and quality. Davidson said a new permanent well will be drilled this spring and it’s anticipated it will be completed by fall. Once completed the existing well will be retired.
Davidson also provided an update on the program to inspect the water lines to homes for lead. He said they are 80% complete and they have only found a few homes with lead pipes coming into the residence. The inspection process should be completed in March and then the city will complete an inventory that will be submitted to the state and they will begin the process of creating a strategic plan to replace the lead lines found.
Caston among school corporations to receive grants from Applause to AG
Prep your vehicle for winter weather
Man arrested after allegedly peeping into windows at multiple Rochester residences
Man dies from injuries sustained in hunting accident in Wabash County
Expanded opportunities for incarcerated Hoosiers through 10-year Ivy Tech partnership
Woman arrested in connection with Olson Road arson
The Andersons, Inc. to acquire Harvestone Low Carbon Partners, expanding ethanol production capacity and low-carbon fuels capabilities
High-paying jobs in advanced manufacturing with Wright Industries expansion