The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.
The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires.
This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod.
The county’s $3 million bridge project is estimated to be completed by October 31.
Gov. Mike Braun orders flags to half-staff for Pearl Harbor Remembrance Day
Stay safe; always assume you are on ‘thin ice’
Light Up the Park kicks off at Rochester City Park with lighting ceremony Dec. 13
Fulton County Public Defenders program to aid new program in Marshall County
Rochester man sentenced to 54 months in prison
100% of Keystone Cooperative member profits returned to farmer-members
More than $320,000 in energy bill assistance available for Duke Energy Indiana customers